Project Update 8/06/2025

The contractors are progressing ahead of schedule on the contract.

Lake County Grading has installed all of the storm sewers and has excavated retention basin C and most of retention basin B and has placed most of the embankment on the project.  They have also completed the placement of the geotechnical fabric, underdrains, and aggregate subgrade for the roadway.

Natural Creations has completed the precast modular retaining wall. See attached photos.

Landmark has completed pouring concrete for the curb and gutter at the Dowell Road Roundabout and is pouring concrete for the retaining wall cap.

Upcoming work will include concrete curb and gutter at Fisher roundabout, median and truck apron stamped colored concrete, lighting, sidewalk, and hot mix asphalt pavement.

Posted in Construction Updates.