Darrell Road has been closed at Case Road and Neville for close to one month. In that time the contractor has completed the following work in the reconstruction area: pavement removal; earth excavation; installation of new drainage system; installation of geotechnical fabric and aggregate subgrade; installation of concrete curb; installation of asphalt binder.
Work expected in the next month includes but is not limited to: installation of stamped concrete median in the splitter islands and truck apron; concrete sidewalks adjacent to the new roundabout; pavement widening and resurfacing at the north leg of Darrell Road to the project limits; installation of light pole foundations, conduit and wiring; grading for and construction of the bike path.
Below are some progress photos from the job site.
![](https://www.darrellroadproject.com/wp-content/uploads/2023/08/IMG_0995-scaled.jpg)
![](https://www.darrellroadproject.com/wp-content/uploads/2023/08/IMG_0986-scaled.jpg)
![](https://www.darrellroadproject.com/wp-content/uploads/2023/08/IMG_1008-scaled.jpg)
![](https://www.darrellroadproject.com/wp-content/uploads/2023/08/IMG_0925-scaled.jpg)