UPDATE 9/21/2023

The contractor completed the Hot Mix Asphalt Surface on 9/18/2023. As work progresses forward, the items to be completed prior to opening the round about include: HMA driveways; shoulder aggregate; landscaping (fertilizer, seed and blanket); fall tree installations; light pole installation; and grooved pavement markings. The lighting service connection from Com Ed will likely be controlling the opening date, as the lighting is required prior to opening the road to traffic. It is anticipated that the Come Ed service connection will be made within 2 weeks.

See below photos from the last week.

Update 09/13/2023

Work completed by the Contractor in August and early September includes: All Excavation; All Concrete Curb, Sidewalk and Stamped Sidewalk; All Underground Electrical Conduit; All Hot Mix Asphalt Binder. The Lake County DOT Crews have installed the signing for the roundabout.  The Landscaping contractor is continuing to install plants, seed and blanket, trees and mulch.  Upcoming work includes: Hot Mix Asphalt Surface, Driveway Pavement, Light Poles and Luminaires, Pavement Markings and Rumble Strips.  The road is still closed to traffic, please follow the posted detour.