Building demolition has been completed. Most of the trees and fence have been removed. Utility relocations should start this month and should be completed by April.
The general contractor, Lake County Grading, is scheduled to close the roads and implement a detour for 140 days starting in June. Depending on the weather, this date may be moved up into May.