Project Update 09/23/2025

Detour is expected to be removed by the end of this week! Work completed includes Lighting; HMA Pavement; Shoulder Stone; Pavement Markings; Sidewalks; and Earth Excavation. Work being completed this week includes Sign Installation; Topsoil Spreading; Tree and Perennial Plantings; Seed and Blanketing; and removal of the Detour.

Project Update 09/15/2025

The contractor is progressing ahead of schedule! The colored stamped concrete truck aprons and medians are complete. All of the underground work for the lighting is complete. The hot mix asphalt surface will be completed early this week, followed by pavement striping. Upcoming work will include Concrete Sidewalks, Landscaping, Light Pole installation and removal of the detour.